The Selangor WTE project achieved significant progress
發布日期:2025-08-28
點擊次數
字體顯示:

【大】

【中】

【小】

馬來西亞雪蘭莪州大型再生能源電站項目于近日取得里程碑式雙突破。8月22日,項目二期工程1#鍋爐水壓試驗一次成功;23日,項目一期工程倒送電工作圓滿完成。兩大核心節點的順利實現,為后續的設備調試與并網發電奠定了堅實基礎。

The large-scale renewable energy power plant project undertaken by the company recently reached two milestone breakthroughs. On August 22, the Phase II project’s #1 boiler hydrostatic test was successfully completed in one attempt; August 23, the back-energization work for the Phase I project was also successfully completed. The smooth achievement of these two core milestones has laid a solid foundation for subsequent equipment debugging and grid connection.

本次水壓試驗是對二期1#鍋爐制造、焊接、安裝質量的一次“大考”。試驗過程中,系統壓力穩步提升至預設最高壓力并保持穩定,所有承壓部件、閥門及焊口無一泄漏,管道無變形,試驗取得圓滿成功。這標志著二期項目全面轉入安裝階段。

This hydrostatic test was a "major examination" of the manufacturing, welding, and installation quality of the Phase II #1 boiler. During the test, the system pressure was steadily increased to the preset maximum pressure and maintained stably. All pressure-bearing components, valves, and welds showed no leakage, and no pipeline deformation occurred, marking the complete success of the test. This indicates that the Phase II project has fully transitioned into the installation stage.

緊隨其后的倒送電工作是項目由建設階段轉向調試階段的關鍵一步。此次操作成功將外部電網電源可靠地接入一期工程的配電系統,意味著電站首次獲得了“外部血液”。主變壓器受電沖擊成功,各項參數正常,電源順利接入6.6KV配電系統。此后,一期項目廠內的各系統設備將陸續獲得電源,逐步開啟單體調試和系統調試工作。

The subsequent backfeeding work is a critical step in the project’s transition from the construction phase to the debugging phase. This operation successfully connected the external grid power supply to the Phase I project’s distribution system reliably, meaning the power plant received "external blood" for the first time. The main transformer underwent a successful energization impact, with all parameters normal, and the power supply was smoothly connected to the 6.6KV distribution system. Thereafter, various systems and equipment within the Phase I plant will gradually receive power, and individual and system debugging work will be initiated step by step.