Major Milestone Reached for Integrated Scheduled Waste Hub Project in Malaysia
發布日期:2025-08-06
點擊次數
字體顯示:

【大】

【中】

【小】

在集團國際化戰略的引領下,公司承擔的首個純海外市政項目取得重要進展。7月16日,馬來西亞危廢綜合處置項目正式啟動清苗工作。這不僅為后續主體工程建設鋪平了道路,也是業主方項目融資的重要里程碑節點。

Driven by the Group’s internationalization strategy, the major milestone for Johor Integrated Scheduled Waste Hub Project has been achieved.On July 16 , land clearing operations officially commenced. This critical step not only paves the way for subsequent main construction works but also marks a vital milestone for the owner’s project financing.

面對全新的海外法規環境與環評(EIA)、規劃許可(KM)等復雜的審批體系,項目團隊深入鉆研當地法規,提前進場協調外部咨詢單位,經過數月攻堅,成功打通了項目開工前最為關鍵的合規性通道,同時逐步厘清了馬來西亞市政項目灌溉與排水(JSP)、污水排放(IWK)、道路接入(JKR)、電力接入(TNB)、供水許可(RSAJ)等審批的全流程脈絡,顯著縮短了審批周期,為項目合法合規開工奠定了堅實基礎,贏得了寶貴時間。

Confronted with unfamiliar overseas regulatory frameworks and complex approval systems–including Environmental Impact Assessment (EIA) and Planning Permission (KM)–the project team conduct in-depth research into local regulations, and coordinating external consultants through early on-site engagement, the team overcame months of obstacles. They successfully navigated the critical compliance pathway essential for project commencement.

Concurrently, the team systematically mapped out the end-to-end approval processes governing key municipal project aspects in Malaysia, including:

? Irrigation and Drainage (Jabatan Pengairan dan Saliran - JSP)

? Sewage Discharge (Indah Water Konsortium - IWK)

? Road Access (Jabatan Kerja Raya - JKR)

? Power Supply Access (Tenaga Nasional Berhad - TNB)

? Water Supply Approval (Ranhill SAJ - RSAJ)

This significantly shortened approval cycles and laid robust groundwork for lawful project initiation.

此次清苗的啟動,不僅為項目的順利推進邁出了至關重要且堅實的一步,更首次系統性地摸清并實踐了純海外市政項目的全鏈條審批流程,積累了寶貴的“從零到一”的實戰經驗,為后續海外項目的快速、合規推進提供了可復制的路徑和強大的信心支撐。

The commencement of site clearing represents not only a crucial stride in project advancement but also our first systematic mastery of the full approval chain for standalone overseas municipal projects. This delivers invaluable implementation experience from zero to one, establishing a replicable pathway for rapid and compliant execution of future international projects.